[Completed] Maintainance Notification 11:00AM GMT Monday 1st March

UPDATE : This maintainence is now underway. All machines have been cleanly powered down. We are currently double checking all systems are powered down and will swap the PDU

UPDATE2: Due to a delay with onsite staff this is taking longer than expected. Appologies for the inconvenience.

UPDATE3: PDU has been replaced and we have connectivity on Edge #1. Servers are now being power cycled.

UPDATE5: All systems are now online and passed sanity checks. IF your VPS is offline please reboot via SolusVM or open a ticket

This is a reminder for the below maintainance which will begin in approx 1hr 45mins

Planned Maintenance Notification for 11:00AM GMT Monday 1st March.

This email is to inform you of some planned maintenance which will be service affecting.

Maintenance:

The main power bar in our rack which is supplied by our data centre has failed. The failure does not affect the power going through and ultimately to our servers however what has failed is the LCD Display which shows the current power usage which is very important to ensure that the rack isn’t overloaded.

Planned for:

11:00AM GMT on Monday 1st March 2010

Expected Downtime:

The downtime expected is approx 10 – 15 minutes. We will be powering all machines down cleanly then replacing the PDU and powering each machine back on.

Note: VPS may take longer due to the way that VPS start up.